Monday, 16 April 2018

Bunglo Ara Pasung 2, Pontian

Membina Dan Menyiapkan Sebuah Rumah Bunglo Satu Tingkat
Nama Pemilik  : En Zainoh Bin Mahat (PTG) & PN Shamsiah Bte Idrus (JAIJ)
Lokasi : Lot PTD 5824, Jalan Pt Sikom, Ara Pasung, Pontian, Johor.
Mula Projek : 17 hb. Mac 2018
Di Jangka Siap :  16 hb. Sept 2018
Keluasan Binaan : 4300 sq.ft
5bilik +1 store + 5 bilik air
Pembiaya : Bendehari Johor
Setting out (17/3/18)
Bakau pile (19/3/18)
Pile cap
Konkrit pile cap (21/3/18)
Stump (23/3/18)
1st. Layer beam (25/3/18)
2nd layer beam (30/3/18)
Back fill (5/4/18)
Racun anai-anai (6/4/18)
Konkrit lantai (10/4/18)
Konkrik lantai (11/4/18)
Tiang (12/4/18)
Brick work (19/4/18)

Bumbung (2/5/18)

Internal plastering (20/5/18)

Roofing (25/7/18)

Siling (28/7/18)

Drain & appron (5/8/18)

Cat (15/8/18)

Cat (18/8/18)

Pagar (21/9/18)

Wednesday, 7 March 2018

Bunglo Rimba Terjun 5

Membina Dan Menyiapkan Sebuah Rumah Bunglo Satu Tingkat
Nama Pemilik  : En. Chipto bin Hj Sumadi (PDRM)
Lokasi : Lot  14362, Lorong HJ Maarof, Mukim Rimba Terjun,  Pontian, Johor.
Mula Projek : 26hb. Feb 2018
Di Jangka Siap :  25 hb. Ogos  2018
Keluasan Binaan : 1700 sq.ft
4bilek +3 Bilik Air 
Pembiaya : Lembaga Pinjaman Perumahan Sektor Awam (LPPSA) 
Cek survey (26/2/18)

Setting out (26/2/18)

Bakau (27/2/18)

Piling & excavate pilecap (28/2/18)

Ground beam (1/3/18)

Backfill (3/3/18)

Brc (4/3/18)
Konkrit lantai (5/3/18)
Tiang (7/3/18)
Brickwall (8/3/18)
Brickwall (11/3/18)
Carporch (13/3/18)
Carporch roof slab (14/3/18)
Kitchen concrete roof slab (15/3/18)
Electrical conduit (19/3/18)
Concrete roof slab (24/3/18)
Kekuda bumbung (26/3/17)
Roof (31/3/18)

Wiring (12/4/18)

Persiapan external plastring (15/4/18)

External plastering (20/4/17)

Tilling (30/5/18)
Internal painting (12/6/18)
Elec fitting (1/6/18)
Anjung (18/6/18)
Aluminium Window (25/6/18)
Table top (27/6/18)
Handing over (29/6/18)