Wednesday, 7 March 2018

Bunglo Rimba Terjun 5

Membina Dan Menyiapkan Sebuah Rumah Bunglo Satu Tingkat
Nama Pemilik  : En. Chipto bin Hj Sumadi (PDRM)
Lokasi : Lot  14362, Lorong HJ Maarof, Mukim Rimba Terjun,  Pontian, Johor.
Mula Projek : 26hb. Feb 2018
Di Jangka Siap :  25 hb. Ogos  2018
Keluasan Binaan : 1700 sq.ft
4bilek +3 Bilik Air 
Pembiaya : Lembaga Pinjaman Perumahan Sektor Awam (LPPSA) 
Cek survey (26/2/18)

Setting out (26/2/18)

Bakau (27/2/18)

Piling & excavate pilecap (28/2/18)

Ground beam (1/3/18)

Backfill (3/3/18)

Brc (4/3/18)
Konkrit lantai (5/3/18)
Tiang (7/3/18)
Brickwall (8/3/18)
Brickwall (11/3/18)
Carporch (13/3/18)
Carporch roof slab (14/3/18)
Kitchen concrete roof slab (15/3/18)
Electrical conduit (19/3/18)
Concrete roof slab (24/3/18)
Kekuda bumbung (26/3/17)
Roof (31/3/18)

Wiring (12/4/18)

Persiapan external plastring (15/4/18)

External plastering (20/4/17)

Tilling (30/5/18)
Internal painting (12/6/18)
Elec fitting (1/6/18)
Anjung (18/6/18)
Aluminium Window (25/6/18)
Table top (27/6/18)
Handing over (29/6/18)




Sunday, 7 January 2018

Bunglo Pt Makuaseng, Benut

Membina Dan Menyiapkan Sebuah Rumah Satu Tingkat
Nama Pemilik  : En Marad bin Jabal
Lokasi : Lorong Hj Rahim, Parit Makuaseng, Benut, Pontian, Johor
Mula Projek : 1hb. December 2017
Di Jangka Siap :  1 hb. April 2018
Keluasan Binaan : 1550 sq.ft
4bilik +3 Bilik Air 
Pembiaya : Sendiri
Bakau pile (1/12/17)
Ground beam 

Pilecap (4/12/17)

Cassaran (8/12/17)
Plastik sheet (12/12/17)
Konkrit lantai (13/12/17)
Tiang (15/12/17)
Dinding RP (22/12/17)
Kuda-kuda & Aluminium foil (26/12/17)
Bumbung (4/1/18)
Plaster dalaman (6/1/18)
Kornis(15/1/18)
Car porch (29/1/18)
Internal painting (15/2/18)
External painting (26/2/18)
Pemasangan barang letrik 
(30/3/18)

Tile (3/4/18)

Kitchen kabinet (8/4/18)

Handing over (12/4/18)





Bunglo Pt Betak, Benut, Pontian

Meroboh, Membina Dan Menyiapkan Sebuah Rumah Bunglo Satu Tingkat
Nama Pemilik  : Ustazah Siti Rashidah Bte Sukemi
Lokasi : TNB PBD76, Kg Parit Betak Darat, Benut,  Pontian, Johor
Mula Projek : 5 hb. December 2017
Di Jangka Siap :  5 hb. Jun 2018
Keluasan Binaan : 2550 sq.ft
4bilik +3 Bilik Air 
Pembiaya : Bendehari Johor
Meroboh rumah lama (5/12/17)

Gali pilecap dan bakau pile (8/12/17)

Ground beam (11/12/17)

Ground beam

Backfill (15/12/17)

Compact (16/12/17)

Plastic sheet & spry anti anai2 (16/12/17)

Konkrit lantai (18/12/17)

Tiang (19/12/17)

Batu rengan (20/12/17)

Dinding (21/12/17)

Dinding (2/1/18)

Roof beam (8/1/18)

Roof fabrication (10/1/18)

Bumbung (22/1/18)

Metal dack (26/1/18)

Wiring (30/1/18)
Internal plastering (3/2/18)

Kornis ( 4/2/18)

External plastering & skim coat
 ( 8/2/18)

Cat dalaman (8/4/18)

Cat luaran dan tingkap (15/4/18)

Pemasangan lampu dan kipas (18/4/18)


Handing over (30/4/18)