Monday 12 December 2016

Bunglo Cikgu Siti Aisah @ Pt Lintang, Air Baloi, Pontian

Membina Dan Menyiapkan Sebuah Rumah Bunglo Satu Tingkat
Nama Pemilik  : Cikgu Siti Asiah Bte Kamilan
Lokasi :  Kg Parit Lintang, Air Baloi, Pontian, Johor
Mula Projek : 23 Nov  2016
Di Jangka Siap :  25 hb. April  2017
Keluasan Binaan : 3200 sq.ft
4bilek +5 Bilik Air 
Pembiaya : Lembaga Pembiayaan Perumahan Sektor Awam
Mobilisation 22/11/16
Bakau pile (23/11/16)
Pilecap/footing (26/11/16)
Ground beam (28/11/16)
Hardcore & compect (2/12/16)
Spray racun anai2 (3/12/16)
Brc (4/12/16)
Slab concrete (5/12/16)
Tiang (6/12/16)
Brick (7/12/16)
Roof beam (13/12/16)
Carporch (16/12/16)
Internal wall plastering (18/12/16)
Roof fabrication (19/12/16)
Roof construction (21/12/16)

Genting (2/1/17)

Internal wall skim coat (12/1/17)
Appron & drain (17/1/17) 
Siling (28/1/17)
Tile bilik air (30/1/17)

Kerja cat (2/2/17)

Table top (6/2/17)

Mosek bilik tidur (7/2/17)

Mosek Ruang Tamu (4/2/17)

Anjung (6/2/17)
Pintu utama (15/2/17)
Dapur (22/2/17)
Lampu & kipas (25/2/17)







Penyerahan (17/3/17)

Tuesday 6 September 2016

Homestay Sawah Datuk, Mersing


Membina Dan Menyiapkan 4 Rumah Berkember @ 8 unit homestay Satu Tingkat
Nama Pemilik  : Ir Tn Hj A Rahman Mohamed
Lokasi :  TNB 11 Kg Tanjung Genting, Sawah Datuk, Mersing
Mula Projek : 25 Ogos  2016
Di Jangka Siap :  25 hb. May  2017
Keluasan Binaan : 1900 sq.ft/blok
3bilek +1 + 2 Bilik Air 
Pembiaya : Bank
www.rumahidaman2u.blogspot.com
Mobilize (25/8/16)
Boundry survey (26/8/16)
Setting out (26/8/16)
Pad excavation B 1&2 (29/6/16)
Konkrit pad footing B1 (29/6/16)
 Ground beam B1 konkrit (2/9/16)
Ready to konkrit 
Ground slab B1 concreting (6/9/16)
Ground beam B 2 concreting (6/9/16)
Konkrit groundbeam B 3 (8/9/16)
Tiang B1 (9/9/16)
Konkrit ground slab B2 (10/9/16)
Brick work B1 (13/9/16)
Tiang B2 (13/9/16)
Excavation pad footing 
B4 (14/9/16)

Blok 1 Roof beam (1/10/16)

Blok 1 - window frane (1/10/16)

Blok 2 - roof beam (3/10/16)

Blok 3 - brick work (2/10/16)

Blok 4 - ground beam (28/9/16)

External plastering - Blok 1(15/10/16)

Metaldack roof - blok 2 (15/10/16)

Roof construction - blok 3 (15/10/16)

Roof beam - blok 4 (15/10/16)

Blok 4 - roof work (10/11/16)

Blok 3 - roof work ( 10/11/16)

Blok 2 - extnal plastering (10/11/16)

Blok 1-  floor rander (10/11/16)

Blok 1 painting work

Blok 2 internal & external skim coat

Block 3 internal plastering

Blok 4 internal plastering

Blok 1 complete (21/12/16)

Blok 2 -95%(21/12/16)

Blok 3 - 75% (21/12/16)

Blok 4 - 60%(21/12/16)
Siap sepenuhnya (27/2/17)